State audit says unsound decision making added billions to bullet train cost

The California High Speed Rail Authority’s decision to start construction on the bullet train in Central Valley ahead of finalizing its plans and obtaining land has led to $600 million in cost overrun, according to a report published Thursday by State Auditor Elaine Howle.